PERMIT TIMELINES
Intake: 2-3 Working Days
Typical Plan Review: Up to 10 Working Days
Larger Plan Review: 10-20 Working Days
Plan Review Letter(s): Up to 3 Working Days After Plan Review
Payment and Issuance: 1-3 Working Days After Approval
EXPIRATION TIMELINES
Permit Intake: 30 Days from application submittal date if incomplete
Plan Review and Issuance: 180 Days from application acceptance letter date
Inspections: 180 Days from permit issuance date for Mechanical and Plumbing stand-alone permits; 365 Days from permit issuance date for all others
Commercial Construction: Timelines for completion of construction following permit issuance are detailed in BMC Chapter 15.27 and are established based on project valuation: 12 months for $0-100,000; 18 months for $1000,001 - $500,000; 24 months for >$500,000.
PERMITTING SERVICES
Permitting in Benicia is fully electronic. No paper plan submittals, resubmittals or revisions will be accepted. All Building Safety applications, plans, and documents must be submitted in Benicia's online permit portal. Please note:
- Large Projects: Submittals for a large project (e.g. a commercial tenant improvement or new residence) require an application along with all supporting documentation (such as Structural Calculations, Title 24 Energy, soils reports) and a completed submittal checklist. Plan review for such projects is 10-20 working days.
- Plan Review Fees: Initial plan review fees cover the first plan review and first recheck. Third and subsequent reviews, and deferred submittals, are charged according to the Master Fee Schedule.
- Electronic File Format: Only PDF and JPG file formats will be accepted for attachments.
- Cut-Off: All submissions after 3:00 PM on a working day will not begin processing until the following working day.
- Permit Center Closures: The Permit Center is closed to new submissions on weekends, holidays, and City Hall closures. During these closure days there will be no permit processing. Please plan accordingly. Click here to view office closure days.
- Time Limitations: Per the Benicia Municipal Code Title 15 and the California Building Code Time Limitation of Applications, applications not issued within 180 days of application shall be deemed abandoned unless a permit extension is issued (requires justifiable cause and processing fee).
Unsure what building permit application to choose:
- Click here for help with residential permits.
- Click here for help with commercial permits.
CONTRACTOR LICENSING SEARCH
Look up a contractor license or Home Improvement Salesperson (HIS) registration to verify information, including complaint disclosure. Before hiring a contractor or signing a contract, CSLB recommends reading the Hiring a Contractor page.
CURRENT CALIFORNIA BUILDING CODE CYCLE
The 2022 CA Building Codes published July 1st, 2022 are in effect and applicable to all building permit applications made on or after January 1st, 2023.
Please also be aware of local regulations that can be found in Title 15 of the Benicia Municipal Code: BMC Title 15
OTHER PERMITTING LINKS AND RESOURCES
Online Permit Center Tutorial Videos
Forms and Information
SolarAPP+ Automated Residential Solar Permitting
Monthly Issued Building Permits
Permit Search by Address