Wastewater Treatment Plant Primary Treatment Rehabilitation Project


1 / 3
Caption Text
2 / 3
Caption Two
3 / 3
Caption Three

Scope

The Wastewater Treatment Plant (WWTP) Primary Treatment Rehabilitation Project consists of repairs to the headworks and primary clarifier structures at the WWTP. The structures have undergone assessment of the condition of their existing coating, concrete, and metallic structures and are in need of repairs, improvements and recoating.

Construction Award Date

December 5, 2023

Tentative Project Schedule

The work is tentatively scheduled to begin May 13, 2024 and be completed in December 2024.

Construction Cost

$2,929,250

Funding Source

Wastewater Major Capital Projects Fund

Contractor

GSE Construction Company, Inc.

Construction Hours

Monday - Friday: 7:00 AM - 4:00 PM

Potential Resident Impact

Minor increased traffic may be experienced along East 5th Street and East G Street, and construction noise may occur during working hours.