Industrial Way Sewer Replacement Project
Scope
The Industrial Way Sewer Replacement Project proposes to replace a single section of existing 10" sanitary sewer main between two existing manholes on Industrial Way near Teal Avenue, within the City Limits.
Construction Award Date
May 6, 2025
Tentative Project Schedule
The work is tentatively scheduled to begin in early Summer 2025 and be completed in 40 working days.
Construction Cost
$454,207.20Funding Source
Wastewater Major Capital Projects Fund
Contractor
A3 Pipeline
Construction Hours
Monday - Friday: 7:00 AM - 4:00 PM
Potential Resident Impact
No residential impacts are anticipated due to construction activities. Minor traffic disruptions are possible in the vicinity of the project during project construction.
Project Contact
Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us