Industrial Way Sewer Replacement Project


1 / 3
Caption Text
2 / 3
Caption Two
3 / 3
Caption Three

Scope

The Industrial Way Sewer Replacement Project included the replacement of a single section of existing 10" sanitary sewer main between two existing manholes on Industrial Way near Teal Avenue, within the City Limits. A3 Pipeline completed the work ahead of schedule and traffic control has been removed. Thank you for your patience during this critical sanitary sewer replacement project!

Construction Award Date

May 6, 2025

Project Schedule

The work began on July 10, 2025 and was completed on July 21, 2025, significantly ahead of schedule.

Construction Cost

$454,207.20

Funding Source

Wastewater Major Capital Projects Fund

Contractor

A3 Pipeline