Industrial Way Sewer Replacement Project

Scope

The Industrial Way Sewer Replacement Project proposes to replace a single section of existing 10" sanitary sewer main between two existing manholes on Industrial Way near Teal Avenue, within the City Limits.

Construction Award Date

May 6, 2025

Tentative Project Schedule

The work is tentatively scheduled to begin in early Summer 2025 and be completed in 40 working days.

Construction Cost

$454,207.20

Funding Source

Wastewater Major Capital Projects Fund

Contractor

A3 Pipeline

Construction Hours

Monday - Friday: 7:00 AM - 4:00 PM

Potential Resident Impact

No residential impacts are anticipated due to construction activities. Minor traffic disruptions are possible in the vicinity of the project during project construction.

Project Contact

Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us

Updates

Updates will be published as information becomes available.