Water Treatment Plant Miscellaneous Mechanical Improvements Project
Scope
The Water Treatment Plant Miscellaneous Mechanical Improvement Project will consist of addressing a wide range of facility issues which include replacement of failed piping underneath the operations building, backwash valve and meter replacement, sedimentation basin isolation from direct filtration process, sedimentation basin slide gate repair, filter slide gate replacement, minor structural repairs to the Raw Diversion Structure, slide gate modifications and replacement at the Raw Water Diversion Structure.
Construction Award Date
February 18, 2025
Tentative Project Schedule
The work is tentatively scheduled to begin in May 2025 and be completed in September 2025.
Construction Cost
$1,088,000Funding Source
Water Major Capital Projects Fund
Contractor
Corcus Construction, Inc.
Construction Hours
Monday - Friday: 7:00 AM - 4:00 PM
Potential Resident Impact
No residential impacts are anticipated due to construction activities.
Project Contact
Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us
Updates
Updates will be published as information becomes available.