Water Treatment Plant Miscellaneous Mechanical Improvements Project

Scope

The Water Treatment Plant Miscellaneous Mechanical Improvement Project will consist of addressing a wide range of facility issues which include replacement of failed piping underneath the operations building, backwash valve and meter replacement, sedimentation basin isolation from direct filtration process, sedimentation basin slide gate repair, filter slide gate replacement, minor structural repairs to the Raw Diversion Structure, slide gate modifications and replacement at the Raw Water Diversion Structure.

Construction Award Date

February 18, 2025

Tentative Project Schedule

The work is tentatively scheduled to begin in May 2025 and be completed in September 2025.

Construction Cost

$1,088,000

Funding Source

Water Major Capital Projects Fund

Contractor

Corcus Construction, Inc.

Construction Hours

Monday - Friday: 7:00 AM - 4:00 PM

Potential Resident Impact

No residential impacts are anticipated due to construction activities.

Project Contact

Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us

Updates

Updates will be published as information becomes available.