Water Treatment Plant Miscellaneous Mechanical Improvements Project

Scope

The Water Treatment Plant Miscellaneous Mechanical Improvement Project consisted of addressing a wide range of facility issues which included replacement of failed piping underneath the operations building, backwash valve and meter replacement, sedimentation basin isolation from direct filtration process, sedimentation basin slide gate repair, filter slide gate replacement, minor structural repairs to the Raw Diversion Structure, slide gate modifications and replacement at the Raw Water Diversion Structure.

Contract Approval Date by Benicia City Council

February 18, 2025 (Agenda Item 12.B)

Project Schedule

Project construction began in April 2025 and concluded in May 2026.

Construction Cost

$1,284,240

Funding Source

Water Major Capital Projects Fund

Contractor

Corcus Construction, Inc.