2024 Citywide Pavement Rehabilitation and Highway Safety Improvement Program (HSIP) Cycle 11 Pedestrian Crossing Project

Scope

The 2024 Citywide Pavement Rehabilitation and Highway Safety Improvement Program (HSIP) Cycle 11 Pedestrian Crossing Project generally consists of pavement rehabilitation, base failure repair, utility adjustment, curb extensions, curb ramps, restriping roadway, and sign replacement.

Construction Award Date

May 7, 2024

Tentative Project Schedule

The work is tentatively scheduled to be performed during BUSD summer recess, beginning June 10, 2024 through September 4, 2024. Work at Rose Drive is tentatively scheduled to be completed by August 12, 2024.

Construction Cost

$1,933,756

Funding Source

Gas Tax, Solid Waste Vehicle Impact Fee, and State funds (for Highway Safety Improvement Program)

Contractor

American Asphalt Repair & Resurfacing Co., Inc.

Construction Hours

Monday - Friday: 7:30 AM - 4:30 PM

Potential Resident Impact

Traffic may be impacted during construction activities along East 2nd Street between Rankin Way, and Rose Drive, on Rose Drive between McAllister Drive and Primrose Lane and on Park Road at Sulfur Springs Creek.

Project Contact

Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us

Updates

Updates will be published as information becomes available.