Military West 12-inch Water Main Replacement Project

Scope

The Military West 12-inch Water Main Replacement Project consisted of replacing a 3,100-foot-long water main along Military West, between West 7th Street and Plaza De Oro. The previous water main was 8-inches in diameter and was increased to 12-inches to provide improved capacity and operational reliability.

Construction Award Date

March 19, 2024

Tentative Project Schedule

The work started in May 2024 and was completed in August 2024.

Construction Cost

The original construction budget was $1,484,938, and the final cost of construction was $1,315,068.

Funding Source

Water Major Capital Projects Fund

Contractor

Koios Engineering, Inc.

Project Contact

Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us