Military West 12-inch Water Main Replacement Project
Scope
The Military West 12-inch Water Main Replacement Project consisted of replacing a 3,100-foot-long water main along Military West, between West 7th Street and Plaza De Oro. The previous water main was 8-inches in diameter and was increased to 12-inches to provide improved capacity and operational reliability.
Construction Award Date
March 19, 2024
Tentative Project Schedule
The work started in May 2024 and was completed in August 2024.
Construction Cost
The original construction budget was $1,484,938, and the final cost of construction was $1,315,068.Funding Source
Water Major Capital Projects Fund
Contractor
Koios Engineering, Inc.
Project Contact
Tony Fisher
City of Benicia
Project Manager
tfisher@ci.benicia.ca.us