Columbus Parkway / Rose Drive Improvement Project
Scope
The Columbus Parkway / Rose Drive Improvement Project increased traffic capacity along Columbus Parkway by providing two through lanes within 700 feet of the Rose Drive intersection. The work included pavement widening, median reconstruction, striping, loop detector replacement, planting and irrigation, curb ramp replacement, utility relocation, and retaining wall construction.
Construction Award Date
May 23, 2024
Project Schedule
The work began on July 8th, 2024 and was completed in November, 2024.
Construction Cost
$1,125,228
Funding Source
Capital Projects Fund
Contractor
Redgwick Construction Co., Inc.