Scope

The Wastewater Treatment Plant Solids Handling Platform Replacement Project will consist of demolition of an existing carbon steel access platform and replacement with a new aluminum access platform. The existing platform has deteriorated and is in need of replacement.

Construction Award Date

June 20, 2023

Tentative Project Schedule

The work is tentatively scheduled to be performed May 20, 2024 through June 7, 2024.

Construction Cost

$218,900

Funding Source

Wastewater Major Capital Projects Fund

Contractor

GSE Construction Company, Inc.

Construction Hours

Monday - Friday: 7:00 AM - 4:00 PM

Potential Resident Impact

Minor increased traffic may be experienced along East 5th Street and East G.

Project Contact

Tony Fisher