2026 Citywide Curb Ramp Project
Scope
The 2026 Citywide Curb Ramp Project includes replacement of 10 curb ramps and 3 driveways at the intersection of Military W and W 10th Street (Site 1), intersection of Corrigan Court and Drolette Way (Site 2), Intersection of Claverie Way and W J Street (Site 3), Intersection of W 5th Street and W J Street, (Site 4), intersection of W 5th Street and W I Street alley (Site 5), intersection of Marina Place and W 4th Street (Site 6), and intersection of First Street and Peggy Martin Lane (Site 7).
Contract Approval Date by Benicia City Council
April 21, 2026
Tentative Project Schedule
The work began in May 2026 and will be completed in August 2026.
Construction Cost
$219,540.75 (budgeted)
Funding Source
TFCA grants, STA microgrant
Contractor
Sposeto Engineering
Construction Hours
Monday - Friday: 7:00 AM - 4:00 PM
Potential Resident Impact
Short pedestrian detours and minor traffic control in the construction areas
Project Contact
Chester Gatdula
City of Benicia
Associate Civil Engineer
cgatdula@ci.benicia.ca.us
Updates
Please use caution around active construction sites.